Oil and gas facility owners and operators face numerous challenges regarding effective corrosion prevention, which can directly impact their ability to operate profitable, safe, and compliant facilities, says corrosion technologies developer Cortec.

Goods receipt, which is often overlooked because of speed and cost considerations, has become a critical factor in the detection of corrosion or mechanical damage in the transported equipment

Goods receipt, which is often overlooked because of speed and cost considerations, has become a critical factor in detecting corrosion or mechanical damage in the transported equipment.

 

Oil and gas facilities are inherently complex operations that require highly engineered, high-cost spares and “low dollar value but high dollar risk parts,” explains Cortec integrity management and preservation solutions VP Bob Boyle.

As these facilities are often situated in remote locations that necessitate long lead times and thousands of line items to allow for the continuous operation of critical systems, companies cannot rely on ‘just-in-time’ manufacturing or logistics processes.

“This results in the standard original equipment manufacturer (OEM) based transit protection being insufficient for oil and gas facilities . . . OEMs design for easier locations and lack the knowledge, experience, or ability to customize their methods for the lead-time challenges posed by, for example, offshore oil and gas facilities,” he elaborates.

Supply Chain Issues

The supply chain has multiple handoff points, making it very challenging for many traditional methods of corrosion prevention to remain intact and effective through transitions – from OEMs, freight forwarders, engineering, procurement, and construction (EPC) contractors, and materials handling at goods receipt, to storage on the shelf.

Goods receipt, which is often overlooked because of speed and cost considerations, has become a critical factor in detecting corrosion or mechanical damage in the transported equipment.

It is often a liability from a handoff perspective because it is usually staffed by personnel who are not expected to thoroughly inspect or identify the spares and often only count and move the items to stockholding facilities.

Goods receipt processes can, however, involve spare parts being inspected competently, as opposed to OEM preservation measures involving packaging and crating products designed only to deliver to the site, not for an extended period beyond.

According to Boyle, the only way to restore a preservation period would involve essentially repairing the damage, replacing the desiccant, and pulling a vacuum again – which is often more expensive and requires materials and tools that are often not located in the goods receipt area.

“Some clients have, therefore, shifted to preservation and goods receipt co-existing, so the right competency is located where it is needed – and 100% quality control can be attained for any items destined for the shelf.”

He adds that, in other cases, preservation is pushed back to suppliers and carefully specified so that the preservation methods can withstand comprehensive inspection processes.

“Proper preservation material selection is the best first step. The material selection and specification process should be specific to the desired ‘pick-and-pull’ strategy, allowing for goods receipt for nonoperating maintenance, audits, inspections on the shelf and staging.”

Proper preservation material selection is the best first step for corrosion prevention.

Proper preservation material selection is the best first step for corrosion prevention.

Noting that it is not always an option to push the corrosion mitigation back onto the supplier, Boyle advises that oil and gas facilities should implement effective financial accountability processes and an on-site corrosion mitigation program that could be co-located with the preservation area.

“When done well, this allows for robust protection that harmonizes with the various touch points for not only goods receipt for material movements or staging for a turnaround but also issuance to operations and returns to stock.”

He adds that goods receipts are an opportunity to reject or return items—an important and “perhaps difficult choice” guided by cost, lead time, and immediate demand—and often do not allow for an effective solution for the operational side of the plant.

Further, with oil and gas facility downtime being “staggeringly expensive”, planned and unplanned downtime and outages form part of an “incredibly tight supply and maintenance schedule”.

Therefore, any part that cannot be installed because of corrosion can cost “thousands in shipping or hotshot costs and disrupt the even more expensive repair schedule”, he says.

Cortec collaborates with suppliers, project owners, and site operators to design practical and cost-effective specifications within cost and operation constraints to ensure corrosion prevention.

Often, the first decision that immediately delivers operational savings is simply having a conversation with subject matter experts, such as Cortec, says Boyle.

In some cases, oil and gas facilities are still subject to engrained habits, such as relying on OEMs and freight forwarders operating well outside of their expertise.

“The primary risk we run into is fear of change, showing up as the “blame game” between OEM and [a] facility.”

Boyle concludes that harmonizing with OEMs and having a proper preservation philosophy and preservation plans from departments will ensure the preservation program’s effectiveness.